skip to content
The Weighted Average

Wire

Oracle flags force majeure on 2.45GW Stargate site

Oracle issued a force-majeure notice tied to its 2.45-gigawatt Project Jupiter Stargate campus in New Mexico, potentially delaying payments if the site misses its 2028 opening, CNBC reports. Oracle says the project remains on schedule, but TechCrunch notes a gas-pipeline delay and pending air-quality permit; data-center operators should treat power delivery and permitting as contractual schedule risk, not back-office cleanup, as AI’s grid bottleneck moves into financing terms.